Plumbing Estimating Checklist: 12 Things to Check Before You Bid

Plumbing bids are often won or lost on details: a riser that was never counted, a gas line hidden in the mechanical sheets, or a grease interceptor shown only on the civil drawings. A short checklist protects your margin. Here are 12 things to check on every plumbing estimate before you submit your number.

1. Read the whole drawing set, not only the P sheets

Plumbing scope shows up on architectural, civil, mechanical, kitchen and even electrical sheets. Floor drains in the architectural plans, water heaters in the mechanical schedules, and utility connections on the civil drawings all belong in your bid if they are in your scope.

2. Count fixtures from the plans and the schedule

Count every water closet, urinal, lavatory, sink, shower, drinking fountain, mop sink and hose bib from the plans, then compare the totals with the fixture schedule. When they disagree, ask an RFI or note the difference in your bid.

3. Check who supplies the fixtures

Owner-furnished fixtures, kitchen equipment supplied by others, and fixtures with special trim change your material cost a lot. Confirm what you buy, what you only install, and what you only connect.

4. Take off domestic water by size and material

  • Cold, hot and hot water return piping, measured by size
  • Pipe material from the specifications (copper, PEX, CPVC or others)
  • Valves, backflow preventers, pressure reducing valves and water hammer arrestors
  • Pipe insulation where the specifications require it

5. Measure sanitary waste and vent, including vertical runs

Waste and vent piping is easy to undercount because so much of it runs vertically. Use the riser diagrams to add stacks, vent through roof, and the drops to each fixture. Include cleanouts, traps and trap primers.

6. Don’t forget storm drainage

Roof drains, overflow drains, storm leaders and the connection to the site storm system are often in plumbing scope. Check the roof plan and the civil drawings to see where your work stops.

7. Find the gas piping

Gas piping to water heaters, rooftop units, kitchen equipment and boilers may be shown on plumbing or mechanical sheets. Measure it by size, and include the meter connection, regulators, shutoff valves and seismic valves where required.

8. Count equipment and specialties

  • Water heaters, boilers, recirculation pumps and expansion tanks
  • Grease interceptors, oil separators and sand traps
  • Sump pumps, sewage ejectors and booster pumps
  • Emergency eyewash and shower stations, and thermostatic mixing valves

9. Confirm the site utilities scope

Find out where plumbing ends: 5 feet outside the building, at the property line, or at the street main. Water service, sewer laterals, tapping fees and meter work can be a large cost if they turn out to be yours.

10. Add the items that are not drawn

  • Sleeves, core drilling and firestopping
  • Hangers, supports and seismic bracing
  • Testing, flushing, disinfection and inspections
  • Saw-cutting, trenching and patching slabs on renovation projects

11. Price labor for the real conditions

Labor depends on pipe material, installation height, building type and access. Underground work, occupied buildings and prevailing wage or union projects need different labor than a simple new building. Price labor hours per item, not only a lump sum.

12. Review against the specifications and addenda

Specifications can change pipe materials, joint types and testing requirements from what the drawings suggest. Check every addendum, then compare your total cost per fixture with similar past jobs as a final check.