A commercial electrical takeoff can include thousands of items across dozens of sheets. Missing a single panel schedule or a fire alarm riser can wipe out the profit on a job. Use this electrical takeoff checklist to make sure your count is complete before you price it.
Before you start counting
- Confirm you have the full set: electrical, architectural, mechanical, plumbing and kitchen sheets, plus specifications and addenda.
- Check the scale on every sheet. Enlarged plans and details are often drawn at a different scale.
- Read the general notes and the electrical legend. They often add requirements that are not drawn.
- Note the scope split: which work belongs to low-voltage, fire alarm or utility contractors.
Lighting and controls
- Light fixtures by type from the plans, checked against the fixture schedule
- Emergency and exit fixtures, and battery or inverter units
- Switches, dimmers, occupancy and daylight sensors
- Lighting control panels, relays and low-voltage control wiring
- Site and parking lot lighting, poles and bases
Power devices
- Receptacles by type: standard, GFCI, USB, dedicated, weatherproof and special-purpose
- Floor boxes, poke-throughs and furniture feeds
- Disconnects and connections for HVAC, plumbing and kitchen equipment
- Motor connections, starters and VFD connections
Equipment connections are easy to miss because the equipment is shown on other trades’ drawings. Cross-check the mechanical and plumbing schedules for every item that needs power.
Distribution equipment
- Switchboards, panelboards and their breakers, from the one-line diagram and panel schedules
- Transformers, meter sockets and utility equipment in your scope
- Generators, transfer switches and UPS systems
- Grounding electrode system, ground bars and bonding
Feeders and branch circuits
- Feeders measured along the real route, including rises and drops at each end
- Parallel sets, which multiply the wire and sometimes the conduit
- Branch circuit conduit and wire, or MC cable where the specs allow it
- Fittings, boxes, supports and pull boxes
- Underground conduit, trenching and concrete encasement
Low voltage and fire alarm
- Data and telecom outlets, cable tray and backboxes with pull strings
- Security, access control and CCTV rough-in
- Fire alarm panel, devices, notification appliances and risers, if they are in your scope
Items that are not drawn
- Firestopping, core drilling and sleeves
- Temporary power and lighting during construction
- Testing, commissioning and as-built drawings
- Permits, inspections and utility fees
- Lifts, scaffolding and equipment rental
Final review
Compare your device counts per square foot with similar past projects, check that every panel in the schedules appears in your takeoff, and confirm the latest addendum is included. Marked-up drawings with each item color-coded make this review much faster.