Plumbing Takeoff: How to Take Off a Commercial Plumbing Job Step by Step

A plumbing bid is only as good as the quantities behind it. Miss one fixture and you also miss its water and waste piping, fittings, carrier and labor. A careful plumbing takeoff counts every fixture, measures every pipe run by system and size, and picks up the fittings, valves and specialties that are easy to skip when you are in a hurry.

This guide walks through how to take off a commercial plumbing job in a logical order, so nothing falls through the cracks.

Before you start the takeoff

  • Confirm the drawing set and addenda. Make sure every plumbing sheet, riser and detail is on the latest issue.
  • Read the specifications. Pipe materials by system (copper, PEX, CPVC, cast iron, PVC, steel), joining methods, insulation, testing and disinfection requirements all change the price.
  • Check the scope split. Roof drains, site utilities, gas service, water heaters and kitchen equipment connections are sometimes by others.
  • Set up your takeoff by system and floor so the numbers are easy to check later.

How to do a plumbing takeoff, step by step

1. Count fixtures from the plans and the fixture schedule

Count every water closet, urinal, lavatory, sink, shower, drinking fountain, mop sink and hose bibb by type. Then check your count against the fixture schedule. The schedule tells you the model, mounting, carrier, faucet and trim, which all affect material and labor. Note which fixtures are furnished by others and only need connection.

2. Measure piping by system and size

Take off each system separately, because each one uses different material and labor:

  • Domestic cold water, hot water and hot water return
  • Sanitary waste and vent
  • Storm drainage and overflow drains
  • Natural gas
  • Condensate, indirect waste and any special systems

Measure along the real route, record every size change, and add vertical risers and drops from the riser diagrams and ceiling heights. Branch lines to fixtures are often not fully drawn, so lay out a realistic route rather than guessing a lump sum.

3. Count fittings, valves and supports

Every pipe run comes with elbows, tees, wyes, reducers, couplings and cleanouts. Count them by size and type, or use your own historical ratios per foot of pipe for each system. Add isolation valves, check valves, balancing valves and pressure-reducing valves from the plans and details, plus hangers, supports, sleeves and firestopping.

4. Take off equipment and specialties

  • Water heaters, booster pumps, recirculation pumps and expansion tanks
  • Backflow preventers, water meters and pressure-reducing stations
  • Grease interceptors, oil and sand interceptors and neutralization tanks
  • Floor drains, floor sinks, trench drains, roof drains and cleanouts
  • Thermostatic mixing valves, trap primers and water hammer arrestors

5. Add insulation, testing and items that are not drawn

Pipe insulation by size and system, pressure testing, disinfection, permits and inspections, excavation and backfill for underground piping, saw-cutting and patching in existing buildings, and core drilling are all real costs that do not appear as lines on the plans.

Commercial plumbing takeoff: common mistakes

  1. Counting fixture symbols but not checking the fixture schedule.
  2. Measuring horizontal piping and forgetting risers and drops.
  3. Counting pipe but not fittings, valves and supports.
  4. Missing connections to equipment shown on other trades’ drawings, such as mechanical make-up water and kitchen equipment.
  5. Leaving out underground work, insulation and testing.

For a printable list of everything to check before bid day, see our plumbing estimating checklist.

Plumbing takeoff FAQ

What is a plumbing takeoff?

A plumbing takeoff is a full list of the quantities on a job: fixtures, pipe by system and size, fittings, valves, equipment and specialties. It is the base for pricing material and labor in a plumbing estimate.

What is the difference between a plumbing takeoff and a plumbing estimate?

The takeoff is the quantities. The estimate adds material prices, labor hours and rates, equipment, permits and overhead to reach a bid price.

How long does a commercial plumbing takeoff take?

It depends on the size of the project, the number of systems and the quality of the drawings. Small tenant spaces can be quick; multi-story buildings with many systems take much longer.

Get a plumbing takeoff for your next bid

MEP Estimation Services provides plumbing estimating services for contractors across the United States, with fixture counts, piping by system and size, fittings and specialties. Need quantities only? See our MEP quantity takeoff services. We also cover electrical and mechanical work as part of our MEP estimating services. You get color-coded marked-up drawings and an Excel file, usually within 24-48 hours.