EV Charging Station Electrical Takeoff: Public Facility in Dublin, California

This project shows how we prepare an electrical takeoff for an EV charging station. The job was a new DC fast-charging installation in the parking area of a public facility in Dublin, California. Our client needed accurate quantities from the electrical drawings to price the work for bid.

Project at a glance

  • Trade: Electrical (Division 26), site power for EV chargers
  • Location: Dublin, California
  • Drawings: Power plan and electrical one-line diagram
  • Deliverables: Color-coded marked-up drawings and an Excel quantity takeoff

Scope of work

  • 5 × 240 kW dual-port DC fast chargers (10 charging ports)
  • New 2500 A, 480/277 V, 3-phase, 4-wire NEMA 3R main switchboard
  • 2500 A shunt-trip main breaker and 5 × 400 A 3-pole feeder breakers
  • Utility pad-mounted transformer and meter
  • Emergency-stop relay and pushbutton, and grounding
  • Underground PVC conduit, feeders, trenching and backfill

Takeoff highlights

ItemQuantity
240 kW dual-port EV chargers5 EA
2500 A main switchboard1 EA
3P 400 A circuit breakers5 EA
3″ PVC conduit694.74 LF
4″ PVC conduit76.93 LF
3/4″ PVC conduit with pull string40.8 LF
3#4/0 + 1#1 Cu THHN/THWN-2 wire694.74 LF each
4#600 + 1#400 kcmil Cu wire76.93 LF each
Weatherproof junction boxes5 EA
Trenching / backfill11.7 CY / 10.4 CY

How we did it

We counted every device and measured every conduit run on the drawings. Each item is color-coded on the marked-up sheets, so the contractor can check every count against the plans. In Excel, the quantities are organized by system (distribution, breakers, EV chargers, grounding, wiring and conduit, earthwork), ready for material and labor pricing.