This project shows how we prepare an electrical takeoff for an EV charging station. The job was a new DC fast-charging installation in the parking area of a public facility in Dublin, California. Our client needed accurate quantities from the electrical drawings to price the work for bid.
Project at a glance
- Trade: Electrical (Division 26), site power for EV chargers
- Location: Dublin, California
- Drawings: Power plan and electrical one-line diagram
- Deliverables: Color-coded marked-up drawings and an Excel quantity takeoff
Scope of work
- 5 × 240 kW dual-port DC fast chargers (10 charging ports)
- New 2500 A, 480/277 V, 3-phase, 4-wire NEMA 3R main switchboard
- 2500 A shunt-trip main breaker and 5 × 400 A 3-pole feeder breakers
- Utility pad-mounted transformer and meter
- Emergency-stop relay and pushbutton, and grounding
- Underground PVC conduit, feeders, trenching and backfill
Takeoff highlights
| Item | Quantity |
|---|---|
| 240 kW dual-port EV chargers | 5 EA |
| 2500 A main switchboard | 1 EA |
| 3P 400 A circuit breakers | 5 EA |
| 3″ PVC conduit | 694.74 LF |
| 4″ PVC conduit | 76.93 LF |
| 3/4″ PVC conduit with pull string | 40.8 LF |
| 3#4/0 + 1#1 Cu THHN/THWN-2 wire | 694.74 LF each |
| 4#600 + 1#400 kcmil Cu wire | 76.93 LF each |
| Weatherproof junction boxes | 5 EA |
| Trenching / backfill | 11.7 CY / 10.4 CY |
How we did it
We counted every device and measured every conduit run on the drawings. Each item is color-coded on the marked-up sheets, so the contractor can check every count against the plans. In Excel, the quantities are organized by system (distribution, breakers, EV chargers, grounding, wiring and conduit, earthwork), ready for material and labor pricing.